If you weren’t aware, there is an extension planned for the Expo line SkyTrain along Fraser Highway from King George Station in Surrey City Centre to Langley Centre.
This expansion would be 16 kilometres in length. It was originally planned to be completed in 2025, however residents will have to wait longer — three full years in fact — as the extension is now expected to be completed in 2028.
Why The Delay?
TransLink planned to complete the first 7 km of the expansion from funding that has now been cancelled. This $1.6 billion of funding was needed to reach the 2025 completion date. Additionally, the original date was pending a business case approval that was scheduled for the summer of 2020. Since neither happened, procurement of a contractor did not occur.
A contractor should have been procured by early 2021 to start construction early 2022. Hence the delays.
To give some scope, the entire project is estimated to be a $3.96 billion cost. Earlier this summer, the federal government announced $1.3 billion to help move the project along. This funding has not yet been formalized. The remaining $2.65 billion would be committed by the provincial government and TransLink.
Worth The Wait?
By 2028, the Expo and Millennium lines will grow to a combined fleet size of 427 cars. Specifically there will be 30 additional cars to serve the Surrey-Langley Extension.
The Surrey City Centre to Langley SkyTrain extension will increase the size of the network by 24%, it will be growing from 66 km to 82 km. This will add 8 new stations into the network from Surrey to Langley.
This means that, when open, there will be a capacity of 6,800 passengers per hour per direction. It also allows for room for growth, so the system can grow with the population and need. When the expansion is complete, its capacity will be more than 10 times the existing bus services along Fraser Highway.
Commuting time will also be cut down. The new travel time of the extended Expo line is expected to be 25 minutes faster than the existing buses. It will also serve those coming into Surrey. With no transfers, getting from Waterfront station in downtown to 166 Street Station in Fleetwood will take under an hour.
The Future is Bright
Once complete the extension will allow for easier access into Surrey Centre and Langley. Ridership is expected to grow in the area, even suggesting that there may be 62,000 daily passengers by the year 2035.
Needless to say, Surrey Centre in coming years will be getting more traffic without the traffic congestion.